Turbines Delivered On Schedule At Coal Clough Windfarm Repowering

ScottishPower Renewables is set to take delivery of eight new wind turbines at Coal Clough Windfarm, near Burnley, as the repowering project moves forward on schedule. The company is replacing 24 wind turbines installed in 1992, with eight modern turbines, which will increase the total generating capacity of the windfarm from 9.6 megawatts to 16 megawatts.

Delivery of the new wind turbine components will commence on the 23rd July 2014 and will be completed over a period of approximately 6 weeks. Daily deliveries will consist of 3 to 4 abnormal loads with a police and haulier escort. These will arrive in convoy so as to avoid extended delays. Deliveries will not take place on Saturdays, Sundays or bank holidays.

The route for delivery of the turbines has been agreed in advance with Lancashire County Council and the police, and follows a number of ‘trial runs’ to prove the suitability of the route. The movement of convoys along the route may result in minor delays. ScottishPower Renewables has carried out works along the route to mitigate these delays, and police escorts on the day will also help ensure free flow of traffic as far as possible.

The deliveries will take place through Brierfield and Burnley between the hours of 9:30am to 3:30pm.

Gerry Gibson, Project Manager at ScottishPower Renewables said: “We are pleased with the progress on the project so far, and have now completed the vast majority of the civil engineering works at site. A great deal of planning has been carried out in relation to the turbine deliveries, and we have worked closely with the local authorities and the police to carefully consider the route and the timings of the deliveries. We would like to thank the community for their co-operation so far, and we hope that our planning will keep any inconvenience to a minimum during the delivery of the wind turbines.”

With the laying of tracks and the wider civil engineering work now nearly complete, and the delivery of turbines starting on schedule, the company is expecting the project being fully commissioned by late autumn.

Source: Scottish Power

For more information on: Scottish Power